Challenge

  • Fouling in heat exchangers impacting temperature control
  • Requirement for controlled execution within a regulated environment
  • Strict adherence to safety and cleanliness standards

Approach

  • Coordination with plant engineering and quality teams
  • Selection of cleaning methodology aligned with equipment sensitivity
  • Planning to minimize disruption to ongoing operations

Execution

  • Controlled hydro jet cleaning by trained technicians
  • Continuous supervision to ensure compliance with site protocols
  • Documentation of cleaning activities and completion

Outcome

  • Restoration of heat exchanger performance
  • Safe execution without impact on plant compliance requirements
  • Improved reliability of utility systems